Project Details - Tata Intellion Park
Tata Intellion Park
Basement, retaining wall, terrace, STP, and UGWT waterproofing work.
Timeline
1 Year
Total Area
2 Lakh Sqft
Budget
2 Crores
Buildings
1
Execution Details
A comprehensive approach to the waterproofing structure utilizing detailed step-by-step methodology to ensure absolute stability and robustness across various functional areas of the facility.
- Basement: HDPE work and chemical grouting work
- Retaining Wall: SBS waterproofing work
- Building: Grinding and micro concrete filling in undulation areas
- STP & UGWT: Internal and top waterproofing work
Project Specifications
Building Type
Commercial
Client
Tata Realty
Location
Mumbai, Maharashtra
Sustainability
Premium Build
Start Date
26-08-2024
Expected Completion
01-04-2027
Project Progress
100%
Step-by-Step Process
Step 1: Surface Preparation
Step 2: Pre-Pond Testing
Step 3: Primer Application
Step 4: Chemical Coating
Step 5: Pond Testing
Step 6: Geotextile Layer
Step 7: Final Finishing
Step 8: Floor Preparation
Step 9: Micro Concrete
Step 10: Chemical Grouting
Step 11: UGWT Work
Step 12: SBS Layer