Project Details - Symbiosis World School
SYMBIOSIS WORLD SCHOOL
Basement, building, terrace, podium, and ramp waterproofing work.
Timeline
2 Years
Total Area
2,00,000 Sqft
Budget
4 Crore
Buildings
5 Buildings
Execution Details
A comprehensive approach to the waterproofing structure utilizing detailed step-by-step methodology to ensure absolute stability and robustness across various functional areas of the facility.
- Basement: Expansion joint, retaining wall waterproofing work
- UGWT: Top and outer shabad waterproofing work
- Building Areas: Toilets, balconies, kitchens, dry balconies, lift pit, domes, entrance gate waterproofing work
- Terrace: Terrace Waterproofing Work
- Podium: Podium Waterproofing Work
- Ramp: Ramp Waterproofing Work
Project Specifications
Building Type
Residential
Client
Symbiosis
Location
Pune, Maharashtra
Sustainability
Premium Build
Start Date
26-08-2024
Expected Completion
01-01-2027
Project Progress
70%
Toilets, Bathrooms & Balcony Waterproofing
Step 1: Surface Preparation
Step 2: Pre Pond Test
Step 3: Chemical Coat
Step 4: Base Coat
Step 5: Brick Bat & Finishing
Step 6: Post Pond Test
Terrace Waterproofing
Step 1: Chemical Coating & Brick Bat Finishing
Podium Waterproofing
Podium Waterproofing Works
Ramp Waterproofing
Step 1: Surface Preparation
Step 2: Primer Application
Step 3: Chemical Coat
Step 4: Geotextile Laying
Step 5: Final Screed
Dome Waterproofing
Step 1: Chemical Coat
Step 2: Brick Bat
Step 3: Final Finishing
Expansion Joint Waterproofing
Expansion Joint Treatment Work