Project Details - Shivatman By Naiknavare
Shivatman By Naiknavare
Terrace waterproofing work.
Timeline
6 Months
Total Area
10,000 Sqft
Budget
38 Lakhs
Buildings
1
Execution Details
A comprehensive approach to the waterproofing structure utilizing detailed step-by-step methodology to ensure absolute stability and robustness across the terrace area of the facility.
- PU Chemical Waterproofing Work
- Brickbat Waterproofing Work
- Crack treatment and joint sealing work
- Terrace surface preparation and finishing work
Project Specifications
Building Type
Residential
Client Name
N/A
Contractor
N/A
Architect
N/A
Start Date
26-12-2024
Expected Completion
01-06-2025
Project Progress
100%