Project Details - Nyati Estaban

Residential

Nyati Estaban

Basement and retaining wall waterproofing work.

Timeline 1 Year
Total Area 25,000 Sqft
Budget 45 Lakhs
Buildings 4

Execution Details

A comprehensive approach to the waterproofing structure utilizing detailed step-by-step methodology to ensure absolute stability and robustness across various functional areas of the facility.

  • HDPE Membrane Waterproofing Work
  • SBS (Bituminous) Membrane Waterproofing Work
  • Retaining wall protection system
  • Construction joint waterproofing treatment
  • Tie rod hole sealing treatment
  • Surface priming and protection work

Project Specifications

Building Type Residential
Client Name N/A
Contractor N/A
Architect N/A
Start Date 26-08-2024
Expected Completion 01-08-2025
Project Progress 50%

Step-by-Step Process

Step 1: HDPE Membrane Waterproofing

Step 2: Retaining Wall Surface Preparation

Step 3: Tie Rod Hole Packing

Step 4: Construction Joint Treatment

Step 5: Surface Priming

Step 6: SBS Membrane Applying

Step 7: Dimple Board Applying