Project Details - Blue Ridge – T16 & T17

Residential

Blue Ridge – T16 & T17

Basement, retaining wall, and podium waterproofing work.

Timeline 2 Years
Total Area 2.5 Lakh Sqft
Budget 3 Crore
Buildings 2

Execution Details

A comprehensive approach to the waterproofing structure utilizing detailed step-by-step methodology to ensure absolute stability and robustness across various functional areas of the facility.

  • Basement: HDPE Waterproofing Work
  • Building Areas:
    • Toilets
    • Bathrooms
    • Dry Balconies
    • Balconies
    • Open Terraces
    • Lift Pit
    • Podium
    • Terrace
    • OHWT Inner & Outer Waterproofing

Project Specifications

Building Type Residential
Client Name N/A
Contractor N/A
Architect N/A
Start Date 26-08-2024
Expected Completion 01-08-2026
Project Progress 90%

Step-by-Step Process

Building Waterproofing

Step 1: Surface Preparation

Step 2: Crack Filling, Angle Fillet & Pipe Packing

Step 3: Chemical 1st Coat

Step 4: Chemical 2nd Coat

Step 5: Brick Bat

Step 6: Finishing

Podium Waterproofing

Step 1: Podium Surface Preparation

Step 2: Crack Opening & Filling

Step 3: 1st Chemical Coat

Step 4: 2nd Chemical Coat

Step 5: Tiyya

Step 6: Screeding & Finishing

OHWT Waterproofing

Step 1: OHWT Surface Preparation

Step 2: Tie Rod Filling

Step 3: 1st Chemical Coat

Step 4: 2nd Chemical Coat

Step 5: Final Plaster

Basement Waterproofing

Step 1: HDPE Waterproofing Work

Lift Pit Waterproofing

Step 1: Lift Pit Waterproofing Work

Expansion Joint Treatment

Step 1: Expansion Joint Waterproofing